Escalation clause in contractors' all risks

The clause that raises the sum insured under a CAR policy automatically as the contract value grows, up to an agreed percentage, so that average does not bite when the project price drifts.

Definition

Munich Re's Contractors' All Risks form asks for a Section I sum insured equal to the full contract value at completion, including materials supplied by the principal, and scales the indemnity down in proportion if that sum turns out to be lower. On a three-year project the price moves with index-linked price adjustment, variation orders and changes in packages. A policy written on the contract price at signing often ends up underinsured without anyone intending it.

The escalation clause deals with that gap in advance. The sum insured rises automatically with the contract value, up to a percentage of the original sum set in the cover note. The insured declares the final value at completion, and the premium is adjusted on that value. Beyond the percentage, average comes back.

The limit of the mechanism is the percentage itself. A contract that drifts past the cap falls back into underinsurance for the excess, and a tunnel or power plant project that gains 30% along the way is never far from that. The clause also tracks contract value, not reinstatement cost, so a jump in steel prices after the loss is not recovered through it.

Example

A hypothetical example, as of December 4, 2025. A €50 million contract insured under a CAR policy with an original sum insured of €50 million and a 10% escalation clause, allowing up to 50 × 1.10 = €55 million. Price adjustments and variations take the contract to €56 million when a fire causes €8 million of damage. The sum insured tops out at €55 million, one million below the actual value, and the indemnity before deductible is 8 × 55 / 56 = €7.857 million. Without the clause it would be 8 × 50 / 56 = €7.143 million. The clause brings back 7.857 − 7.143 = €0.714 million and leaves 8 − 7.857 = €0.143 million of underinsurance with the insured.

Read next
Sources
  • Munich Re, Contractors' All Risks Insurance, standard policy, Section I provisions (sum insured and underinsurance)
  • French Insurance Code, Article L. 121-5 (average)
Related terms
Also known as

escalation clause, sum insured escalation, automatic sum insured increase, CAR escalation clause