Extend or pay demand
A call on a demand guarantee that gives the guarantor the choice of paying or extending the expiry; URDG 758 (article 23) let it suspend payment for up to 30 calendar days, and the counter-guarantor for four days less.
The performance guarantee expires on September 30, the project is six months late and the employer does not want to be left without security. Eight days before expiry, it sends the bank a complying demand that ends with "extend to March 31 or pay." The device is common on public contracts. It confronts the applicant with a full call if it refuses an extension it never asked for or negotiated.
Article 23 of the ICC's URDG 758, in force since July 1, 2010, regulates it. Where a complying demand includes, as an alternative, a request to extend, the guarantor may suspend payment for up to 30 calendar days after receiving it (23(a)). It informs the applicant without delay or, in an indirect structure, the counter-guarantor (23(c)). If the extension is granted within that period, the demand is deemed withdrawn; if not, the guarantor pays without any further demand (23(d)). The guarantor may refuse to extend, even when instructed to, and then pays (23(e)). When the guarantor in turn makes a demand under the counter-guarantee, the counter-guarantor may suspend for four calendar days less than the guarantor did (23(b)), so its answer comes back up the chain before the first period runs out.
ISP98, which govern many standby letters of credit, deal with the same request in rule 3.09. It is examined as a demand for payment, and it implies the beneficiary's consent to the extension requested and the withdrawal of its demand if the extension is issued. An applicant who agrees pays fees on the added period at both ends of the chain, and carries its unfair calling risk for six more months.
In this fictitious example, a €2,000,000 performance guarantee subject to URDG 758 is issued by a local bank against a counter-guarantee from a French bank; the guarantee runs until September 30, 2026 and the counter-guarantee until October 31. On September 22, the beneficiary demands "extend to March 31, 2027 or pay." The local bank suspends payment for 30 calendar days, to October 22, and on September 24 sends a demand of the same kind to the French bank, which may suspend for 26 days, to October 20. The exporter agrees on October 9. Both banks extend, the demands are deemed withdrawn, and the counter-guarantee moves to April 30, 2027 to keep its one-month gap. The extension costs six months of fees at each end, €12,000 at 1.2% a year on the guarantee and €8,000 at 0.8% a year on the counter-guarantee, €20,000 in all.
- International Chamber of Commerce, Uniform Rules for Demand Guarantees, 2010 revision, publication no. 758 (URDG 758), articles 15(b) and 23
- Institute of International Banking Law & Practice, International Standby Practices (ISP98), ICC publication no. 590, rule 3.09
extend or pay demand, extend or pay guarantee, URDG 758 article 23, ISP98 rule 3.09