Intermediate damage (French construction law)
Defects that appear after acceptance, too minor for decennial liability and outside the one- and two-year guarantees, which French case law places under the builder's contractual liability for proven fault, within ten years.
A crack in a facade that does not threaten the structure and lets no water in, found three years after acceptance, fits none of the statutory guarantees. The one-year completion guarantee has run out, decennial liability needs a severity the crack lacks, and render is not an item of equipment that would fall under the two-year guarantee. The third civil chamber of the French Cour de cassation filled that gap. Such defects engage the builder's ordinary contractual liability, on proof of fault, and practitioners call them intermediate damage, sitting between decennial severity and a defect of no consequence.
Article 1792-4-3 of the Civil Code, introduced by the Law of June 17, 2008 reforming limitation periods, sets a ten-year limit from acceptance for actions against builders and their subcontractors, other than those governed by Articles 1792-3, 1792-4-1 and 1792-4-2. The owner gets the same horizon as under decennial liability, without the presumption.
On the insurance side nothing is compulsory. The damage-to-works policy does not pay these defects, nor does the decennial policy, and only an optional extension, if the contractor bought one, picks them up. The expert therefore has to rule on severity before anything else. Classified as decennial, a defect is paid within months by the damage-to-works insurer; classified as intermediate, it starts a lawsuit over fault.
A hypothetical example, as of February 3, 2025. A house accepted on May 10, 2021. The facade render comes away over 140 m², with no water ingress. The repair costs €95 per m², so 140 × 95 = €13,300, plus €4,200 of scaffolding, 13,300 + 4,200 = €17,500 in all. The damage-to-works insurer declines, since the defect is not of decennial severity. The owner sues the rendering contractor in contract; the expert finds the render was applied at 3 °C when the data sheet required at least 5 °C, and that fault decides the case. The contractor had bought the intermediate damage extension with a €1,500 deductible, and the insurer pays 17,500 − 1,500 = €16,000. The action stayed open until May 10, 2031.
- French Civil Code, Article 1792-4-3
- French Law No. 2008-561 of June 17, 2008 reforming limitation periods in civil matters
intermediate damage, intermediate defects, Article 1792-4-3